A comprehensive reimageing of the architect’s own cottage in Redfern. Structural and damp remediation paved the way for new layouts and internal finishes. A tight site with tight tolerances.

Type

Residential Refurbishment

Architect

Trias

Engineer

PMI Engineers

Photography

Joanne Ly

Section C
01

02

03

04

05

06

07

08

Our Impact

Quiet in Tight Conditions

With no off-street parking and extremely limited onsite storage, every material that entered the job came through the front door. Careful sequencing, early trade involvement and off-site prep helped reduce noise, congestion and disruption for both the build team and the neighbours.

Repurposed bedroom floor joists

The existing bedroom floor joists were carefully removed and refinished to form the structure of the outdoor porch roof.

Convict bricks

During construction, convict bricks that were likely laid between 1800's and early 1900's were found. Due to their significance, it was decided that they would be reintegrated into the masonry facade of the cottage.

Courtyard slab

Rather than completely demolishing the entire courtyard slab, Arc. carefully cut out the desired pattern in an attempt to retain as much material as possible.

Our Process

Pre-Construction

1

Preliminary Agreement
Early Contractor Involvement

Attic floor of existing cottage.

Draped House slots between an existing scribbly gum tree.

Early Works

2

Material Reuse & Deconstruction Schedule
Preliminary Agreement
Early Contractor Involvement

Draped House slots between an existing scribbly gum tree.

Draped House slots between an existing scribbly gum tree.

Structure

3

Material Reuse & Deconstruction Schedule
Preliminary Agreement
Early Contractor Involvement

Draped House slots between an existing scribbly gum tree.

Draped House slots between an existing scribbly gum tree.

Enclosure

4

Material Reuse & Deconstruction Schedule
Preliminary Agreement
Early Contractor Involvement

Draped House slots between an existing scribbly gum tree.

Draped House slots between an existing scribbly gum tree.

Interiors

5

Material Reuse & Deconstruction Schedule
Preliminary Agreement
Early Contractor Involvement

Draped House slots between an existing scribbly gum tree.

Draped House slots between an existing scribbly gum tree.

Aftercare

6

Material Reuse & Deconstruction Schedule
Preliminary Agreement
Early Contractor Involvement

Draped House slots between an existing scribbly gum tree.

Draped House slots between an existing scribbly gum tree.